Kitchen renovation

Tracking the full kitchen remodel, demo to final inspection.

Tracked by Demo Owner

Updates

Live
  1. Countertops in, sink connected. Final electrical tomorrow.

  2. Delayed

    Backsplash tile started. Delayed one day — tile shipment short.

  3. Countertop template measured. Quartz slab arrives next week.

  4. Milestone

    Cabinets installed. They look fantastic.

  5. Drywall up and mudded.

  6. Inspection

    Passed rough inspection on the first try.

  7. Rough plumbing and electrical complete. Inspection scheduled.

  8. Resolvededited

    Water damage repaired. Added 2 days to the schedule.

  9. Issue

    Found water damage behind the sink wall. Getting a quote to fix.

  10. Demolition

    Demo day. Old cabinets and counters out by 3pm.

  11. Approved

    Permit approved faster than expected.

  12. Started

    Contract signed with GC. Permit application submitted to the city.