Kitchen renovation

Tracking the full kitchen remodel, demo to final inspection.

Tracked by Demo Owner

Updates

Live
  1. Countertops in, sink connected. Final electrical tomorrow.

  2. Delayedposted Jul-27-26

    Backsplash tile started. Delayed one day — tile shipment short.

  3. posted Jul-27-26

    Countertop template measured. Quartz slab arrives next week.

  4. Milestoneposted Jul-27-26

    Cabinets installed. They look fantastic.

  5. posted Jul-27-26

    Drywall up and mudded.

  6. Inspectionposted Jul-27-26

    Passed rough inspection on the first try.

  7. posted Jul-27-26

    Rough plumbing and electrical complete. Inspection scheduled.

  8. Resolvededitedposted Jul-27-26

    Water damage repaired. Added 2 days to the schedule.

  9. Issueposted Jul-27-26

    Found water damage behind the sink wall. Getting a quote to fix.

  10. Demolitionposted Jul-27-26

    Demo day. Old cabinets and counters out by 3pm.

  11. Approvedposted Jul-27-26

    Permit approved faster than expected.

  12. Startedposted Jul-27-26

    Contract signed with GC. Permit application submitted to the city.